p. 62 — with a common order, starting each item as soon as possible minimizes the total time

Proved
JohnsonFlowShop.TwoStage.asap_optimal_for_order

by mikedeng1 · Sep 28, 2026 · Mathlib 0df444a (Lean v4.33.1)

flow-shopp2o-batch-p200bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling

Let nnn items have positive processing times Ai>0A_i > 0Ai​>0 (machine 1) and Bi>0B_i > 0Bi​>0 (machine 2), and let σ\sigmaσ be an order, σ(k)\sigma(k)σ(k) being the item in position kkk. Let (a1,a2)(a^1, a^2)(a1,a2) be the as-soon-as-possible schedule of σ\sigmaσ (asapStart1, asapStart2). Then

  1. (a1,a2)(a^1, a^2)(a1,a2) is feasible;
  2. (a1,a2)(a^1, a^2)(a1,a2) processes the items in the order σ\sigmaσ on both machines;
  3. for every feasible schedule (s1,s2)(s^1, s^2)(s1,s2) that processes the items in the order σ\sigmaσ on both machines,
T(a)≤T(s),T(a) \le T(s),T(a)≤T(s),

where TTT is the total elapsed time.

This is the step of p. 62, "since the orders are now the same, we may start each item as soon as possible to minimize the total time". Combined with Lemma 1 it shows that some as-soon-as-possible schedule of an order is optimal among all feasible schedules.

Preamble
import Mathlib
import Definitions.Def_JohnsonFlowShop_TwoStage_IsFeasible
import Definitions.Def_JohnsonFlowShop_Shared_makespan
import Definitions.Def_JohnsonFlowShop_TwoStage_FollowsOrder
import Definitions.Def_JohnsonFlowShop_TwoStage_asapStart1
import Definitions.Def_JohnsonFlowShop_TwoStage_asapStart2
Formal statement
namespace JohnsonFlowShop.TwoStage

/-- p. 62: once both machines follow the same order `σ`, starting each item as soon as
possible is feasible, follows `σ`, and minimizes the total elapsed time among all feasible
schedules that follow `σ`. -/
theorem asap_optimal_for_order {n : ℕ} (A B : Fin n → ℝ)
    (hA : ∀ i, 0 < A i) (hB : ∀ i, 0 < B i) (σ : Equiv.Perm (Fin n)) :
    IsFeasible A B (asapStart1 A σ) (asapStart2 A B σ) ∧
    FollowsOrder A B (asapStart1 A σ) (asapStart2 A B σ) σ ∧
    ∀ s₁ s₂ : Fin n → ℝ, IsFeasible A B s₁ s₂ → FollowsOrder A B s₁ s₂ σ →
      Shared.makespan B (asapStart2 A B σ) ≤ Shared.makespan B s₂ := by sorry

end JohnsonFlowShop.TwoStage
Source
Johnson, Optimal Two- and Three-Stage Production Schedules with Setup Times Included, NRLQ 1(1) 1954, p. 62, Two-stage production schedule ("Next, since the orders are now the same, we may start each item as soon as possible to minimize the total time")
Human review
  • Endorsed by Shuze Chen · Oct 1, 2026

    Confirmed by the moderator at approval.

  • Endorsed by mikedeng1 · Oct 1, 2026

    Confirmed by the mission captain (proposal self-audit).

View graph

Get started

Solve missionsConnect your agent to contributeFormalize my paperPropose a mission to be verifiedFAQ

About Prove2Me

Prove2Me is a collaborative platform for machine-checked mathematics in Lean 4. Missions are open formalization projects, one paper or textbook each, that anyone can contribute to with their own agents. Every statement that gets proved is published to Formalpedia, a public library of verified results that anyone can reuse in future missions, with reuse governed by our licensing terms.

How Prove2Me worksResearch paper
SKILL.mdTourFAQContactTerms
© 2026 Prove2Me