Theorem 1 — an order consistent with all definite preferences min(A_i, B_j) < min(A_j, B_i) minimizes the total elapsed time
ProvedJohnsonFlowShop.TwoStage.johnson_rule_optimalLet items be processed first on machine 1 and then on machine 2, one item at a time on each machine, with positive processing times on machine 1 and on machine 2. Item is definitely preferred to item when
and an order ( = the item in position ) is consistent with all the definite preferences when for all positions . Then:
- there is an order consistent with all the definite preferences;
- for every such order , the as-soon-as-possible schedule of (no delays on machine 1; each item starts on machine 2 as soon as it has left machine 1 and machine 2 is free) is feasible, and
where is the total elapsed time, the completion time of the last item on machine 2.
This is Johnson's rule for the two-machine flow shop: the optimal ordering is given by relation (II), with indifferent items placed anywhere consistent with the definite preferences. It is the basis of the three-stage result of the same paper and of the flow-shop scheduling literature.
Formalization Note The comparison is against all feasible schedules (arbitrary start times, possibly different orders on the two machines), not only against permutation schedules. Consistency is required on all pairs of positions: with ties, consistency on adjacent pairs alone does not imply optimality. Part 1 makes the hypothesis of part 2 satisfiable.
import Mathlib import Definitions.Def_JohnsonFlowShop_TwoStage_IsFeasible import Definitions.Def_JohnsonFlowShop_Shared_makespan import Definitions.Def_JohnsonFlowShop_TwoStage_asapStart1 import Definitions.Def_JohnsonFlowShop_TwoStage_asapStart2 import Definitions.Def_JohnsonFlowShop_TwoStage_JohnsonOrdered
namespace JohnsonFlowShop.TwoStage
/-- Theorem 1 (Johnson 1954, p. 63). For positive processing times, (i) there is an order `σ`
consistent with all definite preferences of relation (II), and (ii) for every such order the
as-soon-as-possible schedule of `σ` is feasible and its total elapsed time is at most that of
every feasible two-machine schedule. -/
theorem johnson_rule_optimal {n : ℕ} (A B : Fin n → ℝ)
(hA : ∀ i, 0 < A i) (hB : ∀ i, 0 < B i) :
(∃ σ : Equiv.Perm (Fin n), JohnsonOrdered A B σ) ∧
∀ σ : Equiv.Perm (Fin n), JohnsonOrdered A B σ →
IsFeasible A B (asapStart1 A σ) (asapStart2 A B σ) ∧
∀ s₁ s₂ : Fin n → ℝ, IsFeasible A B s₁ s₂ →
Shared.makespan B (asapStart2 A B σ) ≤ Shared.makespan B s₂ := by sorry
end JohnsonFlowShop.TwoStage