Theorem 1, p. 7 — (7) is a bijection from finite-capacity n-cuts of D onto feasible solutions of (1)–(5), c(X, X̄) = w(x), and min cut = optimum
ProvedProjSchedMinCut.Transform.theorem_1Consider the project scheduling problem with start-time dependent costs: jobs with integral processing times , time lags of integral length requiring , a horizon , and costs for starting job at time . Assume that a feasible schedule exists. Let be the minimum cut digraph of §2.2, built from the earliest and latest feasible start times , . Then:
- the mapping (7),
is a one-to-one correspondence between the -cuts of with finite capacity and the feasible solutions of the integer program (1)–(5); 2. the capacity of such an -cut equals the value of the corresponding solution ; 3. has a minimum --cut, and the capacity of every minimum --cut equals the value of an optimal solution of (1)–(5).
This is the main theoretical result of the paper: the time-indexed formulation of project scheduling with arbitrary time lags and start-time dependent costs is solved by one minimum cut computation, on a digraph with nodes and arcs. It underlies the Lagrangian lower bounds for resource-constrained project scheduling in §3 of the paper.
Formalization Note The one-to-one correspondence is Set.BijOn (maps into, injective on, onto). The standing assumptions of §2 are binders: non-negative weights (p. 5) and the existence of a feasible schedule (p. 4), read within the horizon (, ). The paper's jobs and are artificial with processing time zero; §2.2 never uses this, so it is not assumed (the statement is stronger). Capacities are in and compared with through the embedding of . The existence of a minimum cut is stated explicitly.
import Mathlib import Definitions.Def_ProjSchedMinCut_Transform_Setting
namespace ProjSchedMinCut.Transform
open Instance
/-- Theorem 1, p. 7: the mapping (7) is a one-to-one correspondence between the `n`-cuts of `D`
of finite capacity and the feasible solutions of (1)–(5); the capacity of such a cut equals the
cost of its image; and the capacity of a minimum `a`-`b`-cut equals the value of an optimal
solution of (1)–(5). -/
theorem theorem_1 {n : ℕ} (I : Instance n) (hw : ∀ j t, 0 ≤ I.w j t)
(hfeas : ∃ S, I.Feasible S) :
Set.BijOn I.xOfCut {X | I.IsNCut X ∧ I.cutCap X < ⊤} {x | I.IPFeasible x} ∧
(∀ X, I.IsNCut X → I.cutCap X < ⊤ →
I.cutCap X = ENNReal.ofReal (I.cost (I.xOfCut X))) ∧
((∃ X, I.IsMinCut X) ∧
∀ X, I.IsMinCut X → ∃ x, I.IsOptimal x ∧ I.cutCap X = ENNReal.ofReal (I.cost x)) := by sorry