Section 2.1, p. 291 — restricting big operations to the grid costs at most
ProvedJobShopLTAS.Core.restrictedOpt_leLet , , , and . Then feasible restricted schedules of the jobs exist, and the restricted optimum satisfies
Here is the infimum of the makespans of the feasible schedules of in which every big operation starts at the beginning of an interval of the first type, and is the optimum makespan of the whole instance (all jobs).
The restricted problem is the one the rest of the paper's algorithm solves, and this bound is what makes that restriction affordable.
Formalization Note. The existence clause is what makes (an infimum) a genuine optimum value rather than the junk value of an empty infimum. on the right is that of the full job set; the paper uses the same symbol without distinguishing it from the optimum of , which is no larger.
import Mathlib import Definitions.Def_JobShopLTAS_Core_Instance import Definitions.Def_JobShopLTAS_Core_RestrictedProblem
namespace JobShopLTAS.Core
/-- §2.1, p. 291: restricted schedules exist, and
`C̃*_max ≤ C*_max + µmεP_max ≤ (1 + µmε) C*_max`, where `C̃*_max` is the optimum over
restricted schedules of `B ∪ T` and `C*_max` the optimum of the whole instance. -/
theorem restrictedOpt_le {m n : ℕ} (inst : Instance m n) (ε α : ℝ)
(hm : 2 ≤ m) (hμ : 1 ≤ inst.maxOps) (hε : 0 < ε) (hε1 : ε < 1)
(hα_lo : ε ^ ⌈(m : ℝ) / ε⌉₊ ≤ α) (hα_hi : α ≤ ε) (hP : 0 < inst.Pmax) :
(∃ s : inst.Op → ℝ,
inst.IsFeasibleSchedule (inst.bigJobs α ∪ inst.tinyJobs ε α) s ∧
inst.IsRestricted ε α s) ∧
inst.restrictedOpt ε α ≤
inst.optMakespan Finset.univ + (inst.maxOps : ℝ) * m * ε * inst.Pmax ∧
inst.optMakespan Finset.univ + (inst.maxOps : ℝ) * m * ε * inst.Pmax ≤
(1 + (inst.maxOps : ℝ) * m * ε) * inst.optMakespan Finset.univ := by sorry
end JobShopLTAS.Core
Read-back
What the Lean code literally says, in plain math · claude-opus-5-5
Setup. Take a job-shop instance:
- machines and jobs;
- job has operations on machines with real processing times ;
- ;
- ;
- is the maximum machine load, where a machine's load is the sum of over its operations.
Take reals and write (natural ceiling).
Hypotheses.
Job sets.
Interval grid.
Schedules. A schedule gives every operation a real start .
- It is feasible for a job set when:
- starts of operations of jobs in are ;
- consecutive operations of a job in satisfy ;
- distinct operations of jobs in on the same machine do not overlap: one ends no later than the other starts.
- It is restricted when every operation of a job in starts at for some natural .
- is the maximum of over operations of jobs in , or if there are none.
- is the infimum of over schedules feasible for all jobs.
- is the infimum of over schedules feasible for that are also restricted.
Claim. Three statements hold together:
- Some schedule is feasible for and restricted.
- The restricted optimum is bounded as follows:
- The same bound is in turn at most :
Degenerate cases.
- Under the hypotheses , so , , and no division by zero occurs.
- , since .
- Part 1 guarantees the set defining is non-empty, so it is not the empty-set default of .
- would default to only if no feasible schedule of all jobs existed.
- Jobs in neither nor are ignored in .
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.