Proof of Lemma 11 —
ProvedFlowJobShop.PairGroups.algorithmH_finishTime_leapproximation-algorithmsflow-shopp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let be a flow shop with processors and jobs, and for every group let be a feasible schedule of the flow shop on the processors , with finish time . Let be the schedule generated by algorithm H from these group schedules. Then
This is the upper bound on the heuristic's finish time used in the proof of Lemma 11.
Formalization Note is written (m + 1) / 2 in , which equals for every , and is cast to . The maximum has baseline , as in the lower bound.
Preamble
import Mathlib import Definitions.Def_FlowJobShop_PairGroups_FlowShop import Definitions.Def_FlowJobShop_PairGroups_AlgorithmH
Formal statement
namespace FlowJobShop.PairGroups
open FlowShop
/-- Proof of Lemma 11 (p. 49): the schedule generated by algorithm H from feasible group
schedules `R g` satisfies `FT(S) ≤ Σ_g f(R(g)) ≤ ⌈m/2⌉ · max_g f(R(g))`, where `⌈m/2⌉` is
`(m + 1) / 2` in `ℕ`. -/
theorem algorithmH_finishTime_le {m n : ℕ} (F : FlowShop m n)
(R : (g : Fin ((m + 1) / 2)) → Fin (groupSize m g) → Fin n → ℝ)
(hR : ∀ g, (F.group g).IsFeasible (R g)) :
F.finishTime (F.algorithmH R) ≤ ∑ g, (F.group g).finishTime (R g) ∧
∑ g, (F.group g).finishTime (R g) ≤
(((m + 1) / 2 : ℕ) : ℝ) * (Finset.univ : Finset (Fin ((m + 1) / 2))).fold max 0
(fun g => (F.group g).finishTime (R g)) := by sorry
end FlowJobShop.PairGroups
Source
Gonzalez, Sahni, Flowshop and Jobshop Schedules: Complexity and Approximation, Operations Research 26(1) (1978), p. 49, §2, proof of Lemma 11