Proof of Corollary 2.2, p. 706 — a job known to be last can be removed and the rest scheduled optimally
ProvedEmmonsTardiness.EDD.last_job_reductionConsider a finite set of jobs on one machine with processing times and due dates , and any loss function ; a schedule is optimal if it minimizes , .
Suppose is last in some optimal schedule of . If is an optimal schedule of the remaining jobs (with the same processing times and due dates), then the schedule
is an optimal schedule of .
This is the step "Remove it from the problem, redefine , and repeat" of the proof of Corollary 2.2: once a job is known to be last, the problem reduces to the remaining jobs, whose completion times are unchanged by appending at the end.
Formalization Note No property of or of the processing times is needed. "Redefine " is automatic: the total processing time of the reduced problem is the sum over .
import Mathlib import Definitions.Def_EmmonsTardiness_EDD_Model
namespace EmmonsTardiness.EDD
/-- Emmons 1969, p. 706, proof of Corollary 2.2, last sentence ("Remove it from the problem,
redefine p, and repeat"): if some optimal schedule of `J` ends with `J_j`, then appending `J_j`
to any optimal schedule of the remaining jobs `J \ {J_j}` gives an optimal schedule of `J`. -/
theorem last_job_reduction {ι : Type*} [DecidableEq ι] (g : ℝ → ℝ) (p d : ι → ℝ)
(J : Finset ι) (j : ι) (hj : j ∈ J)
(hlast : ∃ l : List ι, IsOptimal g p d J l ∧ l.getLast? = some j)
(l' : List ι) (hl' : IsOptimal g p d (J.erase j) l') :
IsOptimal g p d J (l' ++ [j]) := by sorry