p. 220, conditions (2)–(4) — if x_j = x_k and a_j, a_k > 0, no y_jk satisfies (2), (3) and (4)
ProvedManneJobShop.Formulation.equal_start_infeasiblebig-minteger-programmingp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let and be integers and positive integers. If two tasks start on the same day, , then there is no integer with
So Manne's constraints (2)–(4) forbid two tasks on the same machine from starting on the same day, as the either-or condition (1) demands.
Formalization Note The positivity is the paper's setting (each task occupies the machine for a positive integral number of days) and is necessary: with the value satisfies both inequalities when . The common start day is the single variable , so the differences and appear as .
Preamble
import Mathlib
Formal statement
namespace ManneJobShop.Formulation
/-- Manne (1960), p. 220: if `x_j = x_k` (both equal to `x`) and the durations are positive, no
integer `y_jk` with `0 ≤ y_jk ≤ 1` satisfies both (3) and (4). -/
theorem equal_start_infeasible (T aj ak x : ℤ) (haj : 0 < aj) (hak : 0 < ak) :
¬ ∃ y : ℤ, (0 ≤ y ∧ y ≤ 1) ∧
(T + ak) * y + (x - x) ≥ ak ∧ (T + aj) * (1 - y) + (x - x) ≥ aj := by sorry
end ManneJobShop.Formulation
Source
Manne, On the Job-Shop Scheduling Problem, Operations Research 8 (1960), p. 220, conditions (2)–(4), "Hence if (x_j − x_k) = 0, there is no value that can be assigned to y_jk"