Theorem 2, p. 8 — some optimal sequence runs a ρ-maximal initial set of a module consecutively, before the rest of the module
ProvedLawlerWCT.SeriesPar.theorem_2Throughout, is a finite set of jobs to be sequenced on a single machine, is an acyclic digraph on (job must precede job when there is a directed path from to ), job has a processing time and a real weight , and the cost of a feasible sequence is , where is the completion time of when the machine starts at time and never idles.
Let be a job module of and let be a -maximal initial set of (Definition 3). Then there is an optimal sequence for in which the jobs of form a consecutive subsequence preceding all other jobs of :
This is the result behind composite jobs: once a -maximal initial set is identified, its jobs may be merged into a single job.
Formalization Note -maximal initial sets are nonempty and are compared with nonempty initial sets only ( in Lean). The page remarks that Sidney states this for a minimal -maximal initial set of ; the statement here is the page's, for an arbitrary -maximal initial set of an arbitrary module.
import Mathlib import Definitions.Def_LawlerWCT_SeriesPar_Model
namespace LawlerWCT.SeriesPar
theorem theorem_2 {ι : Type*} [DecidableEq ι] (N : Finset ι) (G : ι → ι → Prop)
(hGN : ∀ i j, G i j → i ∈ N ∧ j ∈ N) (hacyc : ∀ j, ¬ Relation.TransGen G j j)
(p w : ι → ℝ) (hp : ∀ j ∈ N, 0 < p j)
(M : Finset ι) (hM : IsModule G N M)
(I : Finset ι) (hI : IsRhoMaximal G p w M I) :
∃ τ : List ι, SingleMachinePrec.Biclique.IsOptimalSchedule G p w N τ ∧
∃ a b c : List ι, τ = a ++ b ++ c ∧ (∀ j, j ∈ b ↔ j ∈ I) ∧
∀ m ∈ M, m ∉ I → m ∈ c := by sorry
end LawlerWCT.SeriesPar