Lemma 1: overestimation iff demand is below the baseline
ProvedDRBaseline.lemma_1demand-responseelectricitymechanism-designoperations-researchp2o-gran-per-chapterp2o-plan-paperp2o-v1
Let , , , and , and let be any solution of the customer's problem . Then
- if , the estimated reduction exceeds the actual one: ;
- if , it does not: .
So the baseline decides whether the firm over- or under-credits the customer, and by how much ( or ).
Differences from the source:
- encoding: s∗ = arg max, a single function → every solution of the customer's problem (IsCustomerOptimal); reason: the arg max has ties at up to two ω per (b, r); any two selections differ on a null set, so every integral is the paper's
- encoding: a given baseline b, rebate r, demand ω → b ≥ 0, r ≥ 0, ω ∈ [0, 2Ω]; reason: the firm's domain and the support of f (p.7)
Preamble
import Mathlib import Definitions.Def_DRBaseline_IsCustomerOptimal
Formal statement
namespace DRBaseline
/-- **Lemma 1: over- and underestimation of the demand reduction.**
Agrawal, Yücel, *Design of Electricity Demand-Response Programs*, manuscript of May 26, 2021, Lemma 1, p.13; proof p.OA1.
For a baseline `b ≥ 0`, a rebate `r ≥ 0`, a demand realization `ω ∈ [0, 2Ω]` and any solution
`x` of the customer's problem: if `ω < b` then `S(x) > x`; otherwise `S(x) ≤ x`.
**Formalization Note** `S(x) = (b − (ω − x))⁺` is `estReduction b ω x`; the statement holds for
every maximizer, since `s*` can have ties. -/
theorem lemma_1 (Ω cs b r ω x : ℝ) (hΩ : 0 < Ω) (hcs : 0 < cs) (hb : 0 ≤ b) (hr : 0 ≤ r)
(hω0 : 0 ≤ ω) (hω2 : ω ≤ 2 * Ω) (hx : IsCustomerOptimal cs b r ω x) :
(ω < b → x < estReduction b ω x) ∧ (b ≤ ω → estReduction b ω x ≤ x) := by sorry
end DRBaseline
Source
Agrawal, Yücel, Design of Electricity Demand-Response Programs, manuscript of May 26, 2021, Lemma 1, p.13; proof p.OA1
Human review
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.