Lemma 5.4 — if no B-job can end last, every optimal schedule ends with a longest A-job
ProvedTwoAgentSched.ParetoTotal.lemma_5_4Consider an instance of with -jobs, positive processing times and nondecreasing cost functions , and suppose the instance is feasible. Let be the total processing time of all jobs. If
then in every optimal schedule the last job is a longest -job, i.e. an -job with for every -job .
Applied to the jobs not yet scheduled, this is why the -jobs of an optimal (and of a nondominated) schedule are in SPT order, the fact §11.2 opens with.
Formalization Note The statement is the same as the milestone TwoAgentSched.TotalMax.lemma_5_4 of mission 3 of this series, restated here because draft items cannot import each other. The hypothesis excludes the empty instance, whose empty schedule has no last job; positivity of the processing times is the paper's standing convention.
import Mathlib import Definitions.Def_TwoAgentSched_ParetoTotal_Model
namespace TwoAgentSched.ParetoTotal
/-- Lemma 5.4 (Agnetis et al. 2004, §5.2, p. 234). Consider a feasible instance of
`1‖ΣC^A_i : f^B_max ≤ Q` with at least one A-job, and let `τ = P_A + P_B`. If every B-job has
`f^B_k(τ) > Q`, then in every optimal schedule the last job is a longest A-job: an A-job `h`
with `p^A_{h'} ≤ p^A_h` for every A-job `h'`. -/
theorem lemma_5_4 {nA nB : ℕ} (hA : 0 < nA) (p : TwoAgentSched.MaxMax.Job nA nB → ℝ) (hp : ∀ j, 0 < p j)
(fB : Fin nB → ℝ → ℝ) (hfB : ∀ k, Monotone (fB k)) (Q : ℝ)
(hfeas : TwoAgentSched.TotalMax.IsFeasibleInstance p fB Q)
(hall : ∀ k : Fin nB,
Q < fB k (∑ h : Fin nA, p (Sum.inl h) + ∑ k : Fin nB, p (Sum.inr k))) :
∀ l : List (TwoAgentSched.MaxMax.Job nA nB), TwoAgentSched.TotalMax.IsOptimal p fB Q l →
∃ h : Fin nA, l.getLast? = some (Sum.inl h) ∧
∀ h' : Fin nA, p (Sum.inl h') ≤ p (Sum.inl h) := by sorry
end TwoAgentSched.ParetoTotal