p. 65, worked example — the order (5, 1, 4, 3, 2) takes 47 units, the reversed order 78
ProvedJohnsonFlowShop.TwoStage.example_p65flow-shopjohnson-rulep2o-batch-p200bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Consider the five items of Johnson's example, with processing times
| item (paper) | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 4 | 4 | 30 | 6 | 2 | |
| 5 | 1 | 4 | 30 | 3 |
For an order , write for the total elapsed time of its as-soon-as-possible schedule. Then
- the order has ;
- its total delay (idle) time on machine 2 is ;
- the reversed order has ;
- every order satisfies .
So , the order the working rule produces, is optimal and the reversed order is the worst possible.
Formalization Note Items are 0-based in Lean: the paper's order is the permutation with (position item) and the reversed order is . "Optimal" and "worst" are stated over all orders with their as-soon-as-possible schedules.
Preamble
import Mathlib import Definitions.Def_JohnsonFlowShop_Shared_makespan import Definitions.Def_JohnsonFlowShop_TwoStage_asapStart2
Formal statement
namespace JohnsonFlowShop.TwoStage
/-- The worked example of p. 65, with items renumbered 0–4: `A = (4, 4, 30, 6, 2)`,
`B = (5, 1, 4, 30, 3)`. The order `(4, 0, 3, 2, 1)` (the paper's `(5, 1, 4, 3, 2)`) has
as-soon-as-possible total elapsed time 47 and total machine-2 idle time `47 - ∑ B = 4`; the
reversed order `(1, 2, 3, 0, 4)` has 78; every order has total elapsed time between 47 and 78. -/
theorem example_p65 :
let A : Fin 5 → ℝ := ![4, 4, 30, 6, 2]
let B : Fin 5 → ℝ := ![5, 1, 4, 30, 3]
let σ : Equiv.Perm (Fin 5) := ⟨![4, 0, 3, 2, 1], ![1, 4, 3, 2, 0], by decide, by decide⟩
let τ : Equiv.Perm (Fin 5) := ⟨![1, 2, 3, 0, 4], ![3, 0, 1, 2, 4], by decide, by decide⟩
Shared.makespan B (asapStart2 A B σ) = 47 ∧
Shared.makespan B (asapStart2 A B σ) - ∑ i, B i = 4 ∧
Shared.makespan B (asapStart2 A B τ) = 78 ∧
∀ ρ : Equiv.Perm (Fin 5),
47 ≤ Shared.makespan B (asapStart2 A B ρ) ∧ Shared.makespan B (asapStart2 A B ρ) ≤ 78 := by sorry
end JohnsonFlowShop.TwoStage
Source
Johnson, Optimal Two- and Three-Stage Production Schedules with Setup Times Included, NRLQ 1(1) 1954, p. 65, worked example (table of A_i, B_i)